AON Glasgow


Services


Location

Glasgow


Client

AON


A full strip-out was required around the central core to make way for the client’s new  meeting rooms, as well as new carpets, two new kitchens and two sliding folding walls. From an M&E persepctive, we were to strip out all the existing and increase capacity to support the desk & meeting room layout, replace some existing fan coil units in key areas, and a new condenser installed on the roof to support the cooling system in the newly formed comms room.

Four weeks into the project COVID-19 brought the UK into lockdown. Upon the government’s announcement on the twenty-third of March it was decided to temporarily shut down the project until the situation became clearer. Fortunately, in the weeks leading up to the government’s announcement (and for the entirety of the project), no cases were reported from the BOLP team, or any of our sub-contractor colleagues.

When the project was resumed on the twenty-ninth of June, we were faced with delayed deliveries, furloughed sub-contractors, as well as new building management rules affecting transportation of materials to the ninth floor. However, the experienced BOLP team on took all these issues in their stride, reacting quickly and anticipating unforeseen issues. Hard work and constant communication helped us to navigate this uncharted territory and produce a superb finish.

Workwithus

Get in touch today. Let's get the ball rolling!

Give us a call

0207 6807151

Drop us an email

[email protected]

Get in touch

Fill out the form below and we will get back to you as soon as we can.

* This form collects your name, email and telephone no. so that we can contact you regarding your enquiry.

0207 6807151

[email protected]